Chevron Faces Midnight Deadline in $19 Billion Ecuador Judgment

Source: 

Environmental News Service – http://ens-newswire.com/?p=47609

Date of publication: 
6 August 2012

LAGO AGRIO, Ecuador – U.S. oil giant Chevron has until midnight tonight to pay a US$19.04 billion Ecuador court judgment for polluting Amazon waterways or officially default and face another lawsuit to seize its assets, this time in Ecuador. Such collection lawsuits are pending against Chevron in Canada and Brazil.

Ecuador Judge Liliana Ortiz on Friday signed an order giving Chevron until midnight tonight to deposit the funds necessary to remediate the oil contamination, which included the dumping of more than 16 billion gallons of toxic waste from oil production into Amazon waterways.

Judge Ortiz’s order comes after almost 19 years of litigation.

The case, Aguinda v. ChevronTexaco, began on November 3, 1993 when 30,000 indigenous people and farmers from Ecuador’s Amazon filed a class action suit against Texaco in New York federal court alleging massive oil contamination of the rainforest.

For 10 years, Texaco argued before U.S. judges that the case should be transferred to Ecuador’s courts. In 2002, a U.S. federal judge granted Texaco’s motion and removed the case to Ecuador on the condition that Texaco submit to jurisdiction there and be bound by any ruling of the Ecuadorian courts.

In the meantime, Chevron bought Texaco in 2001, assuming its liabilities and defense of the case.

Texaco operated in Ecuador from 1964 to 1992, building hundreds of oil production facilities. The trial judge in Lagio Agrio found overwhelming evidence that the company dumped billions of gallons of toxic waste into Amazon waterways as a cost-saving measure.

Five indigenous groups in the area have been harmed by the pollution that covers an area the size of Rhode Island. The contamination also caused an outbreak of cancer that has killed or threatens to kill thousands of people in the area, according to evidence before the court.

Judge Ortiz’s order is the final step under Ecuador civil procedure to certify the 188-page trial court judgment, which was issued on February 11, 2011. That judgement was unanimously affirmed on appeal in early January. It set the amount of the judgment at $18.2 billion.

Last week, Judge Ortiz raised the final amount of the award to $19.041 billion after calculating various mandatory costs required by Ecuador law.

Chevron stripped most of its primary assets, including service stations, from Ecuador years ago and the company no longer operates in the country.

Pablo Fajardo, the lead Ecuador lawyer on the case, says that for practical purposes, Judge Ortiz’s order allows the rainforest communities to execute the Ecuador judgment against Chevron’s remaining assets in their home country.

Fajardo estimates Chevron’s remaining assets in Ecuador are worth roughly $200 million, including a $96 million court judgment the company won recently in an international arbitration proceeding against Ecuador’s government.

Judge Ortiz’s order also puts the plaintiffs in a stronger legal position to pursue recognition of the Ecuador judgment abroad under various international treaties and domestic law statutes.

Collection lawsuits are pending against Chevron in Canada and Brazil, where the company has billions of dollars worth of assets. The plaintiffs are asking courts to seize to seize these assets to satisfy the judgment and finance a cleanup of the oil contamination, said Fajardo.

“People in Ecuador are dying because of Chevron’s pollution and company’s utter contempt for the rule of law,” said Fajardo. “Chevron is going to have to be forced by courts to comply with its legal obligations.”

Chevron maintains the plaintiffs’ allegations that it is responsible for alleged environmental and social harms in the Oriente region of Ecuador are “false.”

Chevron says the company never conducted oil production operations in Ecuador, and its subsidiary Texaco Petroleum Co. (TexPet) “fully remediated its share of environmental impacts arising from oil production operations, before leaving Ecuador in 1992.”

“After the remediation was certified by all agencies of the Ecuadorian government responsible for oversight, TexPet received a complete release from Ecuador’s national, provincial, and municipal governments that extinguished all claims before Chevron acquired TexPet in 2001,” the company says.

“All legitimate scientific evidence exonerates Chevron and proves that the remediated sites pose no significant risks to human health or the environment,” Chevron says on its website.

If Chevron refuses to pay the court judgment, the company will face a greater risk of liability in the enforcement actions already pending, said Karen Hinton, the U.S. spokesperson for the indigenous and farmer plaintiffs.

If Chevron defaults, Fajardo said his legal team will file court actions to seize the intellectual property rights of various Chevron brands in Ecuador, including Havoline.

Ultimately, Fajardo said he expects that judges in Ecuador and elsewhere will force the auctioning off of Chevron assets so the proceeds can be used to secure the cleanup mandated by the Ecuador trial court.

“Our legal position is getting stronger by the day,” said Fajardo. “What is clear is that in the eyes of the law, Chevron becomes a fugitive from justice at midnight Monday unless it pays the Ecuador judgment in full.”

Ecuador is currently auctioning off drilling rights in several large fields in the Amazon region. Chevron apparently will be left out of the bidding until it pays the full amount of the judgment, a risk factor that has angered institutional shareholders who have called on the company to settle the case.

In May, 40 of Chevron’s institutional shareholders with more than $580 billion in assets under management sent Chevron CEO John Watson a letter urging him to settle the Ecuador case

“In failing to negotiate a reasonable settlement prior to the Ecuadorian court’s ruling against the company, we believe that Chevron’s Board of Directors and management displayed poor judgment that has exposed the Corporation to a substantial financial liability and risk to its operations,” the investors said in their letter.

On June 6, U.S. Congresswoman Jan Schakowsky, an Illinois Democrat, requested that the Securities and Exchange Commission open an investigation to determine if the company is hiding its risks from shareholders.

————————————————-

Brazil court orders Chevron to suspend drilling in light of oil spills

Max Slater – http://jurist.org/paperchase/2012/08/brazil-court-orders-chevron-to-susp...

3 August 2012

[JURIST] A federal court in Brazil on Wednesday ordered Chevron and drilling company Transocean [corporate websites] to suspend all oil drilling in Brazil within 30 days in the wake of two oil spills off the coast of Rio de Janeiro. A judge for Brazil’s Regional Federal Court of the Second Region [official website, in Portuguese] ruled [AP report] that each company must pay 500 million reals, or 244 million dollars, for every day that they do not comply with the suspension. In November, a Chevron appraisal well leaked 155,000 gallons of oil. In March, oil started leaking again from the well and Chevron suspended production in that oil field. In its ruling on Wednesday, the court rationalized that two oil spills in the span of four months demonstrated that Chevron and Transocean cannot operate the wells safely. Chevron plans to appeal the ruling, saying that it complied with all applicable laws and industry standards.

Chevron continues to face legal battles associated with the oil spill last November. In April, a Brazilian prosecutor filed an $11 billion lawsuit against Chevron [JURIST report] after the company reported a new leak [press release] in the Frade oil field. hevron is also currently appealing an $18 billion fine [JURIST report] for pollution in the Amazon jungle. The judgment against Chevron was upheld in January by a three-judge panel of the Provincial Court of Justice of Sucumbios in Lago Agrio, Ecuador. The $18 billion fine, one of the largest in the history of environmental contamination suits, was originally set at $8.6 billion [JURIST report] but was more than doubled for Chevron’s refusal to pay “moral reparations” to the Ecuadorian government, as required by the original ruling. The Amazon Defense Coalition [advocacy website], plaintiffs in the suit, have responded that the first judgment was a reaffirmation of how Chevron’s greed and criminal misconduct in dumping billions of gallons of toxic waste into the river has led to death and disease. Damages were initially awarded in February by the Provincial Court of Justice of Sucumbios which found that Texaco, which was acquired by Chevron in 2001, polluted large areas of the country’s rain forest.